Brighton Goods Bridge, No.6, Battersea, London.

Client: BAMNuttal

British Construction Industry Civil Engineering Project Award Winner 2012. Judges' comment: "A great example of a team pulling together to deliver a hugely complicated and challenging project."

Click to enlarge...

Bridge 6
Bridge 6 044
Bridge 6 023
Bridge 6 041

Removal of three wheel-timber tracks, each 135m long and reinstatement in ballasted track on new structure. All tracks below structure removes in sequence to allow construction of new viaduct span by span. Each span had a seperate blockade.

Southampton Docks Remodelling

Client: Associated British Ports

Click to enlarge...

crossover under construction - southampton before
crossover in use after construction

Construction of new rail offloading facility. 800m of slab-track incorporating two cross-overs and 800m of ballasted sleeper-track and new turnouts. Challenges overcome included working in an active dock-side area and retaining the ability of daily unloading of trains whilst work was proceeding.

Channel Tunnel Rail Link

Client: C.O.R.B.E.R.

Click to enlarge...

relaying in tunnel - CTRL

Renewal of twin-track railway in tunnel below Kings Cross and St. Pancras Stations. Challenges overcome included one-hour access possessions for plant and materials each week of project.

Copyright of McGregor Railway Services Ltd 2011

You are viewing the text version of this site.

To view the full version please install the Adobe Flash Player and ensure your web browser has JavaScript enabled.

Need help? check the requirements page.


Get Flash Player